Pallivasal Extension Scheme cost touched ₹632.5 crore following delays, says Kerala State Electricity Board

GlobeAlert Desk · curated from The Hindu · South Asia

60-MW hydropower project took more than 20 years to complete. The project was originally given administrative sanction for ₹175.86 crore in 2001

GlobeAlert aggregates and classifies open sources; the story above belongs to its publisher. Summaries are machine-generated from the source text. How we score stories.

GlobeAlert context

What the desk knows about this story

Threat level
1 Low

Scored from severity, scale, escalation potential and source agreement. Below the alert threshold.

Sources
1 publisher

Single-source so far. Treat details as unconfirmed until more publishers report.

Category
Business

Not flagged as developing.

South Asia theater · last 7 days
steady · 2 in the last 24h
702
events logged
91
risk index / 100
Wildfires 547Attacks & Assaults 109Shootings 18Kidnappings 11Protests 4
  • Protest activity (75 reports)Protests · India · 48m ago
  • Man stabs 5 cops inside delhi8217s jama masjid police station accused shot while fleeing20261123185033Shootings · India · 1d ago
  • Man attacked with sickles shot at outside pune shivajinagar court assailants fleeShootings · India · 3h ago
See the theater on the live map →

More in Business